Job costing that updates in week three, not month three

You can’t course-correct a job after it closes. Here’s the reporting cadence that actually changes outcomes.

Erica GarmanFinance systems6 min read

The short answer

Job costing only changes outcomes if it lands while the job is still running. A weekly committed-cost view - labor plus committed purchase orders, with everything else accrued - is roughly 95% accurate and available in days rather than weeks. Month-end precision is an autopsy: accurate, complete and too late to affect the result.

Key takeaways

  • Weekly at 95% accuracy beats monthly at 100%.
  • Start with labor and committed POs; accrue the rest.
  • Review with the PM who can still change the outcome.
  • Precision belongs to job close, not job control.

Month-end job costing is an autopsy. It tells you precisely how the patient died.

A weekly committed-cost view is less precise and far more useful: it's wrong by a few percent while there is still time to do something about it.

Weekly vs. monthly, side by side

Weekly committed viewMonth-end actuals
Accuracy~95%100%
Lag2–3 days18–30 days
Can you still act?YesRarely
InputsLabor + committed POsEverything, reconciled

3 wk

Earliest useful signal on a 16-week job

95%

Accuracy from labor + commitments alone

2 days

Target lag on the weekly view

The cadence

  1. 01Monday: labor posts from the prior week's approved time.
  2. 02Tuesday: committed POs and subcontract values refresh.
  3. 03Wednesday: PM reviews variance over 5% with a named action.
  4. 04Month-end: reconcile for accuracy, not for decisions.
Project manager reviewing a weekly cost report
The review only counts if the person in the room can still change the job.

Frequently asked

How often should job costing be reviewed?
Weekly, using committed costs. Monthly actuals are for accuracy and close, not for controlling an active job.
Isn't a 95% accurate report risky?
Only if you treat it as final. Used as a control signal, a 95% accurate report available in two days is worth far more than a perfect report available in four weeks.
Erica Garman

Erica Garman

Finance systems · Tie In

Keep reading

All resources →

Only get emails when it matters

Get the next field note

The jobsite is noisy enough. We keep your inbox clean and only send a short note when we publish something worth your time.